Progress

Bowen Hills VSOThiess John Holland is undertaking the design and construction of Airport Link, Northern Busway (Windsor to Kedron) and Airport Roundabout Upgrade - Australia's largest infrastructure project.

Design and construction of this integrated transport solution, within the densely populated environment of inner-city Brisbane and the northern suburbs, represents one of the most challenging engineering feats in Queensland's history:

  • 25 bridges
  • 15 km of tunnelling
  • Over 7km of new road

This priority transport infrastructure for Queensland will create more than 10,000 direct and indirect jobs.

On its journey from the city to Brisbane' north and east to the airport, the project alignment influences a large number of suburbs which have been grouped within five key precincts:
Bowen Hills; Windsor-Lutwyche; Kedron; Toombul and Airport Roundabout.

Construction of the Airport Link and Northern Busway (Windsor to Kedron) project is scheduled for completion in mid 2012, with the Airport Roundabout Upgrade completed in late 2011.

Construction Timeline

November 2008Premier Anna Bligh turns first sod marking official start to project construction  
December 2008 Drill and blast excavation commenced at Bowen Hills
January - December 2009Construction of cut and cover structure and TBM launch box at Toombul (Kalinga Park)
March 2009First roadheader commenced tunnelling at Truro Street site, Windsor - mid tunnel point
April 2009Roadheader tunnelling commenced at Federation Street site, Bowen Hills  
May 200924-hour tunnelling operations commence across the project
June 2009Roadheader tunnelling commences in Kedron
November 2009First TBM arrives from Germany for assembly
March 2010Second TBM arrives from Germany for assembly
May 2010First TBM lowered in launch box for assembly underground
Mid 2010First TBM commences tunnelling from Kalinga Park, Toombul excavating the eastbound Airport Link tunnel
September 2010Second TBM commences tunnelling from Kalinga Park, Toombul excavating the westbound Airport Link tunnel
Late 2011Airport Roundabout Upgrade scheduled completion
Mid 2012Northern Busway (Windsor to Kedron) scheduled completion
Mid 2012Airport Link road and free-flow tolling system scheduled completion