Thiess John Holland is undertaking the design and construction of Airport Link, Northern Busway (Windsor to Kedron) and Airport Roundabout Upgrade - Australia's largest infrastructure project.
Design and construction of this integrated transport solution, within the densely populated environment of inner-city Brisbane and the northern suburbs, represents one of the most challenging engineering feats in Queensland's history:
This priority transport infrastructure for Queensland will create more than 10,000 direct and indirect jobs.
On its journey from the city to Brisbane' north and east to the airport, the project alignment influences a large number of suburbs which have been grouped within five key precincts:
Bowen Hills; Windsor-Lutwyche; Kedron; Toombul and Airport Roundabout.
Construction of the Airport Link and Northern Busway (Windsor to Kedron) project is scheduled for completion in mid 2012, with the Airport Roundabout Upgrade completed in late 2011.
| November 2008 | Premier Anna Bligh turns first sod marking official start to project construction |
| December 2008 | Drill and blast excavation commenced at Bowen Hills |
| January - December 2009 | Construction of cut and cover structure and TBM launch box at Toombul (Kalinga Park) |
| March 2009 | First roadheader commenced tunnelling at Truro Street site, Windsor - mid tunnel point |
| April 2009 | Roadheader tunnelling commenced at Federation Street site, Bowen Hills |
| May 2009 | 24-hour tunnelling operations commence across the project |
| June 2009 | Roadheader tunnelling commences in Kedron |
| November 2009 | First TBM arrives from Germany for assembly |
| March 2010 | Second TBM arrives from Germany for assembly |
| May 2010 | First TBM lowered in launch box for assembly underground |
| Mid 2010 | First TBM commences tunnelling from Kalinga Park, Toombul excavating the eastbound Airport Link tunnel |
| September 2010 | Second TBM commences tunnelling from Kalinga Park, Toombul excavating the westbound Airport Link tunnel |
| Late 2011 | Airport Roundabout Upgrade scheduled completion |
| Mid 2012 | Northern Busway (Windsor to Kedron) scheduled completion |
| Mid 2012 | Airport Link road and free-flow tolling system scheduled completion |