Community notifications


We will continue to notify local residents, businesses and community groups about construction prior to works being undertaken; these notifications are letterbox dropped to the relevant properties affected and also updated on this site.



Bowen Hills precinct


Type of work Commencing
July Construction update July 2009
Services relocation - Campbell St and Mayne Rd 29 June - 5 July 2009
Site Establishment - land surrounded by Somerset, Albany and Gennon Streets, Windsor June 2009 - June 2012
Night work and Footpath changes - Victoria St site 19 June - 19 July 2009
Tunnelling Works - 24hr works continue 29 June-13 July 2009
June Construction Update - general May-June 2009
Lutwyche Rd eastern pathway closure 4 May 2009 - June 2012

Windsor-Lutwyche precinct

Type of work Commencing
Construction of new Bradshaw St traffic island 26-29 June 2009
Night Works - median strip removal 26-27 June 2009
Traffic signal relocation - Intersection of Bradshaw St and Lutwyche Rd 26 June - 1 July 2009
Night delivery of oversize machinery - Truro St
(Lane closure on Lutwyche Rd southbound)
29-30 June 2009
Lutwyche Rd traffic diversion From 29 June and mid July 2009
Bradshaw St east closed 29 June 2009
Changes to footpaths and bus stops.  
PATHWAY NETWORK - Bradshaw St, cnr Lutwyche Rd/ Bradshaw St and Lutwyche Rd between Bradshaw St and Norman Ave. 
BUS STOPS: Bus Stop 21 - Felix St northbound and Bus Stop 22 - Norman St northbound
Mid June
Lutwyche Rd eastern pathway closure 4 May 2009 - Jun 2012
Services relocation - Kedron to Lutwyche April - June

Kedron precinct

Type of work Commencing
Suez St partial road closure - Gordon Park Mid July - End Aug 2009
July Construction update - Gympie Rd July 2009
Gympie Rd site construction update - Closure of Lasseter St and Gympie Rd worksite update 8 July 2009 - June 2012
Telecommunication relocations - Stafford Rd, Gordon St, Goulburn St, Swan St, Thistle St, Groom St and Kate St. 29 June - 29 Sept 2009
Demolition works - western side of Gympie Rd north of Sadlier St 22 June - 3 August 2009
Telecommunication services work - Gympie Rd to Sadlier St 22 June - 6 July 2009
Park Terrace closure - changes to Lasseter St 27 May 2009


Toombul precinct

Type of work Commencing
Kalinga Park sewer work July - August 2009
July Construction Update - all areas July 2009
Night work along QR corridor 12-13 July 2009
Night Work - Sandgate Rd Telecommunication service relocation 6 July 2009
Telecommunication services work - Widdop St to Gateway Motorway late June - early August
Construction update - general June
Tree transplant in Ross Park 4 June
Construction of sewerage infrastructure - Toombul/Clayfield March - approx 4 months 

Airport Roundabout precinct

Type of work Commencing
Construction Update - July July 2009
Night Work - Barrier Installation
Western side of Gateway Motorway (northbound)
On and off ramps to East West Arterial Rd and Southern side of East West Arterial Rd
2 - 19 July 2009
Site Establishment Update May 2009

Bald Hills


Type of work Commencing
Three month update May - July 2009


All areas

*Please note: these notifications apply to all areas along the project alignment including Bowen Hills, Lutwyche/Windsor, Kedron and Toombul precincts.

Type of work Commencing
Groundwater monitoring March 2009 - ongoing
Condition surveys
ongoing









 